Please note the planning conceptual estimate for the High School Construction Project. Particuliar attention should be given to the line item estimate for Furniture, Fixtures Equipment and Site Development ($1,500,000) & ISDS (septic system) Costs (($1,000,000)). Also, please note the cost estimate allocated for work on the "A" Bldg.
Question: Why was the furniture budget reduced to $500,000, over $1,000,000, in the final budget?
Question: Why did the Town Council have to reallocate $1,000,000 from the school capital reserve fund for the septic system?
Question: Why did the Town Council cut the recommended project funding by $2,000,000? (from $35,000,000 to $33,000,000).
These are but a few on the many questions that I will address in the very near future.
Bill Mudge
NORTH KINGSTOWN HIGH SCHOOL | ||||
Proposed Master Plan | ||||
17-Oct-97 | ||||
CONCEPTUAL ESTIMATE (Prepared by Saccoccio Assoc. Inc.) | ||||
Reported | ||||
Sq. Ft | Cost per | Calculated | Total | |
Gross | Sq. Ft | Total | 17-Oct-97 | |
Demolition | ||||
Administration Building | 4,600 | $8 | $36,800 | |
Cafeteria & 1A Building | 33,219 | $8 | $265,752 | |
Girl's Gym | 15,366 | $8 | $122,928 | |
"E" Building | 4,342 | $8 | $34,736 | |
"B" Building | 10,606 | $10 | $106,060 | |
"H" Building | 10,744 | $10 | $107,440 | |
Central Administration | 13,500 | $8 | $108,000 | |
Total Demolish | 92,377 | $8.46 | $781,716 | $673,716 |
(Note 1) | ||||
Renovations | ||||
"S" Building | 13,796 | $90 | $1,241,640 | |
"A" Building | 89,308 | $90 | $8,037,720 | |
"D" Building | 10,875 | $90 | $978,750 | |
Total Renovations | 113,979 | $10,258,110 | $10,258,110 | |
New Construction | ||||
New 93 Classroom addition | 130,000 | $115 | $14,950,000 | |
Support Space | ||||
Auditorium, Cafe, Admin. | 35,000 | $115 | $4,025,000 | |
Total New Construction | 165,000 | $18,975,000 | $18,975,000 | |
Grand Total's School Construction | ||||
Total Sq. Ft 278,979 | 278,979 | |||
Total School Cost | $30,014,826 | $29,906,826 | ||
Furniture, Fixtures equipment etc. | $1,500,000 | |||
Fees, Engineering, Bond cost etc. | $1,000,000 | |||
Site Development & ISDS system Costs | $1,000,000 | |||
New Central Admin Building | 13,500 | $115 | $1,552,500 | |
$5,052,500 | $5,052,500 | |||
Grand Total | 292,479 | $35,067,326 | $34,959,326 | |
Less New Central Admin Building | $1,552,500 | |||
Grand Total Less New Central Admin Building | $33,406,826 | |||
Budget Deficit | --------------------------------------------------- | (406,826) | ||
Note. 1 Total Demolition cost is in error, it should be $673,716 not $781,716 |